Mahira homebuyers stage protest against delay in flat delivery

The buyers alleged that while the project was to be completed in August 2022, there has been no construction activity for the last 15 months after the authorities suspended the project licence of the developer for allegedly submitting forged documents in May 2022

Updated on: Jul 21, 2023, 23:49:43 IST
Share
Share via
  • facebook
  • twitter
  • linkedin
  • whatsapp
Copy link
  • copy link

Around 200 buyers of Mahira Homes project in Sector 68 gathered at the developer’s office on Golf Course on Friday and carried out a protest against the delay in delivery of flats and lack of construction activities on the site.

Mahira homebuyers stage a protest against the Sector 68 project delay on Golf Course Road on Friday. (Parveen Kumar/ HT)
Mahira homebuyers stage a protest against the Sector 68 project delay on Golf Course Road on Friday. (Parveen Kumar/ HT)

The buyers alleged that while the project was to be completed in August 2022, there has been no construction activity for the last 15 months after the authorities suspended the project licence of the developer for allegedly submitting forged documents in May 2022.

The buyers, including senior citizens and women, carried placards and shouted slogans against the developer, the department of town and country planning (DTCP) and the Haryana government.

The protesters, who went to meet the promoters of the realty firm, alleged that none of them were present.

Dhruv Kapoor, a homebuyer, said the project was launched in 2018 and was to be completed by August 2022. “The flat buyers have paid almost the full amount to the developer, but they are caught in legal trouble as the DTCP has charged the developer with irregularities and suspended the licence last year. It later gave the developer six months to complete the project, but there has been no progress,” he said.

The protesters said they are inconvenienced due to the indifference of the developer as well as the authorities and will further intensify their agitation to get their flats delivered. “We had been running from pillar to post to get out flats. We also went to the state capital Chandigarh to meet Haryana Real Estate Regulatory Authority (H-Rera) officials there,” said another buyer, who requested anonymity.

Around 1,500 homebuyers have invested their money in the Sector 68 project undertaken by Mahira Developers, which got stuck after the DTCP cancelled the licence on May 9, 2022, due to discrepancies in the documents submitted by the developer while obtaining the licence for the project.

However, on September 5, 2022, the cancellation was revoked after the developer assured that the project will be completed in six months, said DTCP officials, adding that action was initiated again as the developer did not comply with the order.

The homebuyers also said that they have held multiple protests at the DTCP office, H-Rera office, and even at the Jantar Mantar in the national Capital, but to no avail. They alleged that despite all their efforts, the developer is yet to resume construction work.

When asked about the concerns of the homebuyers, senior town planner Renuka Singh said that the matter is being monitored at the DTCP headquarters in Chandigarh. “We are providing all details and construction status and updates to the headquarters in Chandigarh. All efforts will be made to ensure that the project is completed in a time-bound manner,” she said.

Meanwhile, DTCP officials privy to the matter said that the department will look into the violations of licence agreements by the developer. The issues between the builder and homebuyers will be primarily handled by the H-Rera, they added.

Meanwhile, Sikander Chokkar, the managing director of Mahira Developers said H-Rera has frozen the escrow accounts of Mahira Homes since May 2022.

“Our accounts are still blocked even after repeated requests. We have sought six months from the town planning authorities and requested them to remove the restrictions so that the work can be completed. A plan on the project completion has also been submitted. I have scheduled a meeting with the allottees at 11:30 am on Sunday. We will definitely deliver the flats soon,” Chokkar added.

  • Abhishek Behl
    ABOUT THE AUTHOR
    Abhishek Behl

    Abhishek Behl is a Special Correspondent with Hindustan Times, Gurugram bureau. With over a decade of experience in journalism, he reports on Gurugram's rapid urban transformation, covering the city's changing infrastructure, governance, and planning landscape. His reporting spans major civic agencies, such as the Gurugram Metropolitan Development Authority (GMDA), Department of Town and Country Planning (DTCP), Haryana Shahari Vikas Pradhikaran (HSVP), and the National Highways Authority of India (NHAI). Behl has reported on key urban development issues such as RRTS projects, metro expansion, road and highway projects, water supply, drainage, mobility, environmental concerns, land use planning, affordable housing, and the city's real estate sector. He closely tracks policy decisions, infrastructure implementation, and their impact on the city and its residents. He also covers regulatory action against illegal constructions, urban flooding, traffic management, and initiatives aimed at improving civic services and sustainable development. Behl has also written on political developments in south Haryana, focusing on elections and governance. His journalism is driven by fact-based reporting, ground-level coverage, and an understanding of the social and economic dynamics of Gurugram. Apart from work he is a cyclist and a cricketer and a resident of Palam Vihar since 2010.Read More